HomeMy WebLinkAboutResolution No. 04-38 RESOLUT,ON NO. 04-3{
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF THE
COLONY, TEXAS, APPROVING THE TERMS AND CONDITIONS OF
THE ENGINEERING SERVICES CONTRACT BY AND BETWEEN THE
CITY OF THE COLONY AND CHIANG, PATEL & YERBY, INC. FOR
DESIGN OF UPGRADED CHLORINATION FACILITIES FOR ALL
THREEE WATER SUPPLY WELL SITES, WHICH IS ATTACHED
HERETO AND INCORPORATED HEREIN AS EXHIBIT "A";
AUTHORIZING THE CITY MANAGER TO EXECUTE THE
CONTRACT; AND PROVIDING AN EFFECTIVE DATE
WHEREAS, the City and Consultant have entered into an agreement such that the
Consultant is to provide the following services: DESIGN OF UPGRADED CHLORINATION
FACILITIES FOR ALL THREEE WATER SUPPLY WELL SITES; and
WHEREAS, the City has determined that it is in the best interest of the City to enter into
the Contract with CHIANG, PATEL & YERBY, INC., which is attached hereto and
incorporated herein by reference as Exhibit "A," under the terms and conditions provided
therein.
WHEREAS, with this Contract the City of The Colony is agreeing to pay a sum not to
exceed $68,664.00 for such work. ~
THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
THE COLONY, TEXAS THAT:
Section 1. The Engineering Services Contract, which is attached and incorporated hereto as
Exhibit "A", having been reviewed by the City Council of the City of The Colony, Texas, and found
to be acceptable and in the best interest of the City and its citizens, be, and the same is hereby, in all
things approved, and the City Manager is hereby authorized to execute the Agreement on behalf of
the City of The Colony, Texas.
Section 2. That this Resolution shall take effect immediately from and after its adoption
and it is so resolved.
PASSED, APPROVED and EFFECTIVE this 17th day of May, 2004.
/~.hn Dillard, Mayor
E : x
~T~~,_A..L [;~ ICity of The Colony, Texas
~-hristtie Wilson, City Secretary
[CITY SEAL]
APPR,~/T~JORM:
obert E. Hag~,~ity Attorney
63918
City of The Colony
Engineering Services Agreement for
Design of Ammonia Feed System at Water Well Sites
Exhibit A
Scope of Services
General
The Project includes the design and development of plans and specifications, suitable for bidding
and construction &Ammonia Feed System for Water Well Sites.
Detailed Scope of Services
1. Preliminary Design
a. Kick-off meeting.
b. Data Collection - Obtain field information of the existing chlorine system and
feed rates at each of the well sites.
c. Develop preliminary plans for review by the City.
d. Conduct a preliminary design review meeting with the City staff to discuss the
City's review comments from the preliminary design submittal.
2. Final Design
a. Prepare plans and specifications suitable for bidding and construction &the new
facilities.
b. Submit the plans and specifications to the City for review and comments.
c. Conduct a design review meeting with the City staff to discuss the City's review
comments fi'om the design submittal.
d. Incorporate the city's comments and prepare final plans and specifications for
bidding.
3. Bidding and Award
a. Assist the City in advertising and receiving bids.
b. Answer any questions from bidders and prepare any required addenda.
c. Attend Pre-Bid Meeting.
d. Review bids received and make a recommendation regarding award of a
construction contract
4. Construction
a. Attend the project Pre-Construction Meeting.
b. Make periodic (approximately monthly) site visits to review the Contractor's
progress and to determine if the construction is being completed in general
conformance with the plans and specifications.
c. Review submittals and shop drawings.
d. Review the contractor's monthly progress payment application and make a
recommendation to the City regarding payments to the contractor
e. Respond to any questions submitted by the contractor regarding the intent of the
plans and specifications.
f. Assist the City in preparing and negotiating any required change orders. Make
recommendations to the City regarding any change orders.
g. Incorporate any construction records submitted by the City or the contractor into
the plans and specifications and submit a set of record drawings.
5. Schedule
a. Consultant will submit the Preliminary Design to the City for review within six
weeks after notice to proceed. Consultant will submit Final Design eight weeks
after the receipt of comments on the Preliminary Design from the City.