HomeMy WebLinkAboutResolution No. 03-08 CITY OF THE COLONY, TEXAS
RESOLUTION NO. ~.~"0
A RESOLUTION OF THE CITY OF THE COLONY, TEXAS,
AUTHORIZING THE ACCEPTANCE OF A CHANGE ORDER TO
THE ENGINEEERING SERVICES AGREEMENT WITH NATHAN
D MAIER CONSULTING ENGINEERS TO INCLUDE
CONSTRUCTION OF OFFICE CREEK PHASES IIA &B;
PROVIDING AN EFFECTIVE DATE.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF
THE CITY OF THE COLONY, TEXAS:
Section 1. That a change order in the amount of $36,500 to the engineering services
agreement with Nathan D. Maier Consulting Engineers for the incorporation of Office
Creek Phases IIA & B is hereby accepted.
Section 2. That a tree and correct copy of the Change Order is attached hereto and
incorporated herein.
Section 3. That this resolution shall take effect immediately from and after its
passage.
PASSED AND APPROVED by the City Council of the City of The Colony,
Texas, this 17th day of March 2003.
Bemetta Henville-Shannon, Mayor
ATTEST:
Patti A. Hicks, TRMC, City Secretary
February 24, 2003
Mr. Gordon Scruggs, P.E.
City Engineer
City of The Colony
6800 Main Street
The Colony, Texas 75056
RE: Memorial Drive Improvements
Blair Oaks Drive to Paige Road (3400' +/-)
Contract Amendment
Dear Mr. Saldana:
Nathan D. Maier Consulting Engineers, Inc. (NDMCE) is pleased to present this proposal to
amend the agreement for engineering and surveying services for the Memorial Drive
Improvements.
UNDERSTANDING OF THE PROJECT
Memorial Drive is proposed to be a six-lane divided urban arterial with curb and gutter, raised
median and an enclosed storm sewer system within a 100' right-of-way. The design of this
project was essentially complete when the project scope was modified. The burrent project is
proposed to design and construct the northern two lanes of the ultimate six-lane street. This
includes survey and hydraulic analysis to accommodate the ultimate roadway project. The
roadway design has been modified to construct the northern two lanes with gabions along the
natural channel of Office Creek and a temporary earth retaining wall along the south right-of-
way line (future centerline). If the City is successful in obtaining a slope easement from the
adjacent property owner, the temporary earth retaining wall will be deleted and a 4:1 side slope
will be used. The water line has been relocated from the north parkway to the median as
instructed by the City.
There are two separate projects underway to construct a channel for Office Creek along the north
side of Memorial Drive from Paige Road to a point west of Blair Oaks Drive. Memorial Drive
will be parallel to and adjacent to the channel. The City wishes to combine the three projects
into a single construction contract. The City has instructed NDMCE to investigate the feasibility
of redirecting the channel from SH 121 to a location adjacent to and parallel to Blair Oaks Drive
and upsizing the culvert to handle the redirected flow. In the original project scope, there are
two major creek crossings included in the Memorial Drive project.
Two NorthPark / 8080 Park Lane I Suite 600 ! Dallas, Texas 75231 ! (214) 739-4741
Mr. Gordon Scruggs, P.E.
February 24, 2003
Page 2
SCOPE OF WORK
1. Paving and Drainage Engineering Design
NDMCE will modify the original engineering design and prepare construction plans for
Memorial Drive from Blair Oaks Drive to Paige Road. The project design will be
modified to delete the southern half of the roadway from the final construction plans and
to include a temporary earth retaining wall along the south right-of-way line so as not to
encroach on the adjacent property. If the City is successful in obtaining a slope easement
from the adjacent property owner, the temporary earth retaining wall will be deleted and
a 4:1 side slope will be used. The roadway cross sections will be modified to reflect the
current design. The culvert design nearest to Blair Oaks Drive will be upsizedto handle
the flow from the relocated SH 121 channel.
2. Project Manual
NDMCE will prepare the project manual and contract documents for Memorial Drive
from Blair Oaks Drive to Paige Road. The project will combine Memorial Drive and the
two Office Creek projects for bid and construction purposes. The City Will provide
construction plans and specifications for the Office Creek project being designed by
Kimley-Horn for inclusion in the contract documents. The contract documents will
utilize NCTCOG standard specifications or other standards specified by the City.
3. Geoteehnieal Investigation
NDMCE will provide geoteehnieal investigation services through a subeonsultant. The
geoteelmieal investigation will provide data to be used in design of the gabion retaining
wall and preparation of pavement subgrade.
COMPENSATION
NDMCE proposes to accomplish the above services for a fixed fee as listed below.
Modify Paving and Drainage Engineering Design $ 26,500.00
Prepare Contract Documents $ 3,500.00
Water Line Engineering Design $ 6.500.00
TOTAL AMENDED BASIC SERVICES $36,500.00
Reimbursable expenses, including reproduction, mileage and deliveries will be billed at the rate
of actual cost plus 15%. Any services requested but not defined in the scope of services above
Mr. Gordon Scruggs, P.E.
February 24, 2003
Page 3
will be performed on an hourly basis or an agreed lump sum fee. Hourly items will be billed in
accordance with our schedule of fees and charges in Attachment "A".
PAYMENT
Invoices for services outlined in this proposal will be submitted, with supporting information as
appropriate, on the first day of each month and are due within 30 days of receipt.
TERMINATION OF SERVICES
In connection with the services to be provided to you by NDMCE, we agree that you may cancel
or indefinitely suspend further work or terminate this agreement, or any portion of it, upon
written notice of thirty (30) days to NDMCE, with the understanding that immediately upon
receipt of such notice, all work being performed under this proposal or any portion of it shall
cease. Before the end of such thirty-day period, NDMCE shall provide an invoice for all work
completed and shall be compensated accordingly for all work accomplished by us prior to the
receipt of such notice.
ACCEPTANCE
We are pleased to have the opportunity to submit this proposal and look forward to working with
you on this project. If you have any questions about this proposal, I would be pleased to discuss
them with you at your convenience. If you are in agreement with the contents of this proposal,
please add your signature and return one copy to our office.
Sincerely,
NATHAN D. MAIER
Gordon J. Maye'bJr.4', P.E. '~
GJM/klb
This p~[~osal is accept.ed,
%3 b 0
ATTACHMENT "A"
NATHAN D. MAIER
CONSULTING ENGINEERS, INC
SCHEDULE OF FEES AND CHARGES
The following Schedule of Fees and Charges shall be modified on January 1, 2004.
Principal $100.00 - $160.00 / hour
Expert Testimony $195.00 / hour
Registered Engineer $75.00 - $125.00 ! hour
Registered Surveyor $70.00 - $110.00 ! hour
Engineer $50.00 - $90.00 / hour
Senior Designers $70.00 - $85.00 / hour
Technician $55.00 - $80.001 hour
Drafter $40.00 - $55.00 1 hour
Field Party $115.001 hour
Secretarial/Word Processing $45.001 hour
Construction Manager $85.00 - $90.00/hour
Construction Inspector $60.00 - $80.00~ hour
Reimbursables ,
1. Direct costs, such as reproductions, equipment rental, delivery SerVices,
travel expenses, or subcontractor services will be billed at actual cost plus
15%.
2. Unless otherwise stated, statements will be submitted monthly for charges
incurred during the month and payments will be due within thirtY (30)daYs
following receipt of the statements.
Effective January 1, 2003
ENGINEERING DEPARTMENT
ENGINEERING SERVICES CONTRACT APPROVED BY CITY COUNCIL
FOR CITY MANAGER'S SIGNATURE
PROJECT NAME: Chanqe Order for Memorial Drive Improvements
CONTRACTOR: N.D. Maier Consultinq Engineers
CONTRACT A~OUNT: $36,500.00
DATE APPROVED BY CITY COUNCIL: 3/17/03
MINUTES ATTACHED: YES X NO (NOT COMPLETE)
OTHER COMMENTS:
City Secretary